Staff from PIE International Limited formed a team with Bioflow Limited to refurbish a sewage treatment plant at a Public School, which had repeatedly failed its discharge consent to a local stream. The existing plant was undersized, and suffered inadequate primary treatment. Solids carried over to the secondary stage resulting in an overloaded biological filter and poor effluent quality. The existing sewage treatment system was redesigned and a novel primary settlement tank was designed and installed which incorporated a novel, floating, decant facility which optimised solids solubilisation. The existing biological filter situated at a remote part of the site, was also refurbished and increased in diameter. As a result, the plant was effectively upgraded to a population equivalent of 200. After completion of the refurbishment programme, the plant was monitored
during its commissioning stage, and found to be well within consent
limits. The plant has maintained compliance since completion.
|
||
|
|||
|
|